Acquisition of works for execution of the bicycle lane from Timisoara to Serbian border
Banat River Basin Administration
The project consist into bicycle lane along the Bega river, having 2 to 2.5 m width and 36 981 km length, located on the crowning of the dam. Road systems consists of a layer of foundation of ballast to the thickness of 10 cm, a base coat of crushed stone in thickness of 15 cm and a wear layer of asphalt concrete in thickness of 4 cm. To protect structure will be foreseen 14 barriers operated manually, to all the major roads and side access. The materials of works amounting more than 100 000 to, according to the bill of quantities. There are more than 37 000 to of ballast and more than 45 000 to of crushed stone which have to be transported for 50 km. Also, there are almost 8 700 to of asphalt concrete to be layered to the approx. 37,0 km of the crowning. The Contracting Authority has some requests regarding the access to the site in order to preserve the existing parameters of the dam – its resistance structure, access platforms and existing slopes – so, during the periods of rainfall (spring, fall, winter) the dam is impassable, leading to a cessation of the activity.
Termen limităTermenul de primire a ofertelor a fost de 2014-04-17. Achiziția publică a fost publicată pe 2014-02-11.
Cine? Ce?- • Lucrări de construcţii de autostrăzi şi de drumuri › Drumuri şi alte suprafeţe pietruite › Lucrări de construcţii de piste de biciclete
| Data | Document |
|---|---|
| 2014-02-11 | Anunţ de participare |
Obiect
Domeniul de aplicare al achiziției
Titlu: Lucrări de construcţii de piste de biciclete
Metadate ale anunțului
Limba originală: engleză 🗣️
Tip de document: Anunţ de participare
Natura contractului: Lucrări
Reglementare: Nu se specifică
Vocabular comun privind achizițiile publice (CPV)
Cod: Lucrări de construcţii de piste de biciclete 📦
Procedura
Tip de procedură: licitaţie deschisă
Tip de ofertă: Prezentare ofertă pentru toate loturile
Criterii de atribuire
Cel mai mic preţ
Autoritatea contractantă
Identitate
Țara: România 🇷🇴
Tip de autoritate contractantă: Minister sau orice altă autoritate naţională sau federală
Numele autorității contractante: Banat River Basin Administration
Adresa poștală: 32 Mihai Viteazu Bvd
Cod poștal: 300222
Orașul poștal: Timisoara
Contact
E-mail: catalin.aldescu@dab.rowater.ro 📧
Telefon: +40 256491843 / +40 256491848 📞
Fax: +40 256491798 📠
Referință
Date
Data trimiterii: 2014-02-11 📅
Termen-limită de depunere: 2014-04-17 📅
Data publicării: 2014-02-13 📅
Identificatori
Numărul anunțului: 2014/S 031-049336
Număr JO-S: 31
Obiect
Domeniul de aplicare al achiziției
Scurtă descriere:
Număr de referință: 1378/Banat River Basin Administration/09.
Denumirea proiectului sau a programului finanțat de UE: Romania — Republic of Serbia IPA Cross-border Cooperation Programme.
Locul de desfășurare
Locul principal sau locul de desfășurare: Dam of Bega River, Downstream Timisoara, Romania.
Informații juridice, economice, financiare și tehnice
Executarea contractului
Depozite și garanții solicitate: 25 000.00 EUR.
Procedura
Perioadă de valabilitate a ofertei: 90 zile
Data deschiderii ofertelor: 2014-04-17 📅
Locul deschiderii:
Limbi
Limbă: engleză 🗣️
Autoritatea contractantă
Identitate
Numărul național de înregistrare: 18263352
Contact
Punct de contact: 32 Mihai Viteazu Bvd, Timisoara, Romania
Aldescu Catalin
URL al documentelor: http://www.rowater.ro/dabanat/Proiect%20Pista%20de%20cicloturism%20pe%20Bega/Forms/AllItems.aspx 🌏
Referință
Identificatori
Număr de referință atribuit de autoritatea contractantă: 1378/Banat River Basin Administration/09.
Sursa: OJS 2014/S 031-049336 (2014-02-11)