Execution works for investment objectives (Bridge over the Nera river, border crossing point, connection road to DN57A)
The contract is going to be awarded to successful tenderer in order for Contracting Authority to be able to construct bridge over the Nera River, on the DN 57A route at km 25 + 530 and bridge ramp and border crossing point. The bridge will have a length of 79.13 m. Carriageway width is 7.80 m with sidewalks of 1.50 m. Detailed information can be found in the technical design attached.
Termen limită
Termenul de primire a ofertelor a fost de 2015-07-06.
Achiziția publică a fost publicată pe 2015-04-29.
Cine?
Ce?
Unde?
Istoricul achizițiilor
Data |
Document |
2015-04-29
|
Anunţ de participare
|
2015-07-07
|
Informaţii suplimentare
|